Current Service Interruption

Electrical Shutdown, Saturday, December 21, 2024 between 7:00-8:30am, CPH

Where is this happening?

Carl Pollock Hall (CPH)
Second Floor

What is happening?

Electrical Shutdown

When is this happening?

Saturday December 21st from 7:00am-8:30am

How does this affect the UW community?

Second floor power will be offline during this time to install new breakers for panel feeder.
120/208 Volt Panels: P2379-3 (Rm2379), P2369D-1 (Rm2369D), P2372E-1(Rm2369G), P2372A-1(Rm2373F), P2373-1(Rm2373D), P2376A-1(Rm2376F), P2368-1A(Rm2387), P2368A-1(Corridor 2368A), P2367-1(Rm2367), P2368-1(Mech Rm 2368), MCC-2368 (Mech Rm 2368)

Who to contact for more information?

Dan MacGibbon
dmacgibbon@uwaterloo.ca

This work must be performed at this time, and cannot be rescheduled.

More Service Interruptions

August 1, 2024 - Pedestrian Bridge connecting Lot A & CPH will be closed. Bridge Closures, Friday, October 25, 2024 - Late 2026/Early 2027, M3, MC, DC Road Closure, Monday, November 11 -Tuesday, December 31, 2024, OPT, UWD, Lot O and X Electrical Shutdown, Saturday, December 21, 2024 between 7:00-8:30am, CPH Electrical Shutdown, Sunday, December 22, 2024 from 8:00am - 2:00 pm, MC Perimeter Heat Shutdown, Monday, December 23, 2024 between 8:00am - 12:00 pm, NH Electrical Shutdown, Friday, January 3, 2025, between 8:00-9:00am, South Campus Hot Water Supply, Monday, December 30, 2024 from 7:00am -7:00pm, QNC Fire Alarm Testing, Wednesday, January 1, 2025 between 6:30-8:15am, PHR, IHB, OSC - Innovation Arena Fire Alarm Testing, Wednesday, January 1, 2024 between 10:00-11:00am, UC, BAU, AVR Maintenance Water Supply, Thursday, January, 2, 2024 between 3:00-7:00pm, ARC Maintenance of Hot Water, Thursday, January 2, 2025 between 7:00 - 11:00am, DWE C-wing Maintenance of Hot Water, Thursday, January 2, 2025 between 12:00 - 4:00 pm, DWE Hot Water Maintenance, Friday, January 3, 2025, between 7:00-11:00am, DWE Fire Alarm Testing, Friday, January 3, 2025 between 6:30-8:15am, ERC, M3, BMH Fire Alarm Testing, Friday, January 3, 2025, between 1:00-2:30pm, MH, MKV, REV Electrical Shutdown, Saturday, January 4, 2025 from 7:00am - 1:00pm, QNC Fire Alarm Testing, Monday, January 6, 2025 between 6:00-8:00, QNC Fire Alarm Testing, Monday, January 6, 2025 between 6:30-8:15am, PAS, HH, TC, AL Fire Alarm Testing, Monday, January 6, 2025, between 100:00-11:00am, EC1, 2 & 3 Electrical Shutdown, Tuesday, January 7, 2025 between 7:00-8:00am, B2 Electrical Shutdown, Wednesday, January 8, 2025 between 6:00-8:00am, NH Fire Alarm Testing, Wednesday, January 8, 2025 between 6:30-8:15am, PAC, SLC, RAC1, RAC2, FED Hall Electrical Shutdown, Sunday, January 12, 2025 between 8:00am - 12:00pm, ML, EV1 Electrical Shutdown, Tuesday, January 14, 2025 between 7:00-8:00am, B2 Electrical Shutdown, Sunday, January 19, 2025 between 8:00am -12:00pm, ML Electrical Shutdown, Sunday, February 2, 2025 between 8:00am - 12:00pm, NH Electrical Shutdown, Sunday, March 16, 2025 between 8:00am- 2:00pm, TC Electrical Shutdown, Sunday, April 27, 2025 between 8:00am - 1:00 pm, REV Electrical Shutdown, Sunday, May 11, 2025 between 7:00am - 12:00 pm, CIF, BH Electrical Shutdown, Sunday, June 22, 2025 between 7:00am- 12:00pm, SCH, GH Electrical Shutdown, Sunday, July 20, 2025 between 7:00am - 1:00pm E3 Electrical Shutdown, Thursday, August 17, 2025 between 7:00am-1:00pm, E2, E3 Electrical Shutdown, Sunday, August 17, 2025 between 7:00am-1:00pm, E2, E3 Electrical Shutdown, Sunday, September 14, 2025 between 7:00am-1:00pm, CPH, DWE Electrical Shutdown, Sunday, October 26, 2025 between 7:00am-1:00pm, EV1, AL Electrical Shutdown, Sunday, November 23, 2025 between 7:00am-1:00pm, EV2, EV3 Electrical Shutdown, Sunday, December 7, 2025 between 7:00am-1:00pm, UWD Brightstarts