Service Interruption Notice

Maintenance is being done on the switchgear to correct a manufacturer defect.

Updates

** 3RD UPDATE **
AUGUST 25, 2022 Electrical shutdown 6:00PM TO 4:00AM – No longer required as everything was completed in last night’s shutdown.

** 2ND UPDATE **
**DATE AND TIME CHANGED **
AUGUST 24, 2022 Electrical shutdown 6:00PM TO 4:00AM
AUGUST 25, 2022 Electrical shutdown 6:00PM TO 4:00AM

Where is this happening?

The following buildings will be affected:
- Tatham Centre Co-op & Career Services (TC-45)
- South Campus Hall (SCH-16)
- Carl A. Pollock Hall (CPH-29)
- Engineering 2 (E2-02)
- Engineering 3 (E3-03)
- Dana Porter Library (LIB-08)
- Needles Hall (NH-31)
- Douglas Wright Engineering (DWE-01)
- Graduate House (GH-104)
- PHY SHARC-4A
- Physics (PHY-04)
- Centre for Environmental & Information Technology (CEIT-39)
- J.R Coutts Engineering Lecture Hall (RCH-11)
- DC CIM-37A

What is happening?

Maintenance is being done on the switchgear to correct a manufacturer defect.

When is this happening?

** 3RD UPDATE **
AUGUST 25, 2022 Electrical shutdown 6:00PM TO 4:00AM – No longer required as everything was completed in last night’s shutdown.
** 2ND UPDATE **
**DATE AND TIME CHANGED **
AUGUST 24, 2022 Electrical shutdown 6:00PM TO 4:00AM
AUGUST 25, 2022 Electrical shutdown 6:00PM TO 4:00AM

How does this affect the UW community?

Power will be shutdown to the following buildings:
- Tatham Centre Co-op & Career Services (TC-45)
- South Campus Hall (SCH-16)
- Carl A. Pollock Hall (CPH-29)
- Engineering 2 (E2-02)
- Engineering 3 (E3-03)
- Dana Porter Library (LIB-08)
- Needles Hall (NH-31)
- Douglas Wright Engineering (DWE-01)
- Graduate House (GH-104)
- PHY SHARC-04A)
- Physics (PHY-04)
- Centre for Environmental & Information Technology (CEIT-39)
- J.R Coutts Engineering Lecture Hall (RCH-11)
- DC CIM-37A

Who to contact for more information?

Danica Beggs (dbeggs@uwaterloo.ca)
x41092

This work must be performed at this time, and cannot be rescheduled.