Service Interruption Notice
Shoring Work, Monday, November 10, 2025 - Thursday, January 1, 2026, RAC1
Where is this happening?
North parking lot at RAC-1
What is happening?
Shoring / Early works - WaterFEL
When is this happening?
November 10th, 2025 - January 1st, 2026
How does this affect the UW community?
Please be advised of the upcoming construction activities associated with the shoring and early works phase:
-Shoring / Early Works: November 10 – November 15, 2025
-Pile Driving: Mid-December (approximately 5 days)
-Lagging / Tiebacks: End of December 2025
-Traffic Restrictions / Limited Access (While Equipment and materials are delivered): Mid-December – Late December 2025
These activities may result in excessive noise, vibration, and restricted access in and around the work area.
Who to contact for more information?
Dan MacGibbon
dmacgibbon@uwaterloo.ca
This work must be performed at this time, and cannot be rescheduled.